Buildings and Facilities17GE0140

CONSTRUCTION OF SCHOOL BUILDINGS FUNDED UNDER 2017 BEFF (BATCH 3) COMPLETION OF FOUR STOREY 20CL G.I. ROOF SCHOOL BUILDING, TRINIDAD V. CANJA-STA. TERESA NATIONAL HIGH SCHOOL

CONSTRUCTION OF SCHOOL BUILDINGS FUNDED UNDER 2017 BEFF (BATCH 3) COMPLETION OF FOUR STOREY 20CL G.I. ROOF SCHOOL BUILDING, TRINIDAD V. CANJA-STA. TERESA NATIONAL HIGH SCHOOL is a DPWH-tracked public work in Guimaras DEO, Region VI. Reported contract value: ₱5,201,646.98. Status: Reported complete (DPWH). Contractor on record: J E TICO CONST CO INC FORMERLY: JET CO. Figures trace to dpwh.

Guimaras DEO, Region VI
Region: Region VI

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Tastasan Flood Project, Buenavista, Guimaras
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXIII-17-0012440

₱7,553,738.00 · FY2017

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱5,201,646.98

Progress

Reported complete (DPWH)

Start Date

December 29, 2017

Target End

April 27, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.