Roads24NE0026

REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE, DINAGAT-LORETO ROAD, K0060+650 - K0060+750, LIBJO, DINAGAT ISLANDS

REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE, DINAGAT-LORETO ROAD, K0060+650 - K0060+750, LIBJO, DINAGAT ISLANDS is a DPWH-tracked public work in Dinagat Islands DEO, Region XIII. Reported contract value: ₱19,364,496.12. Status: Reported complete (DPWH). Contractor on record: HEAVY JOHN ENGINEERING CONSULTANCY 41939. Figures trace to dpwh.

Dinagat Islands DEO, Region XIII
Region: Region XIII

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱19,364,496.12

Progress

Reported complete (DPWH)

Start Date

March 4, 2024

Target End

July 31, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.