Water Provision and Storage19JA0181

CONSTRUCTION OF RAINWATER COLLECTOR SYSTEM AT LUMAYANG ES, MANGGA ES, CRISTINO M. PARAGAS ES, SAN JOSE GUSU ES, SHIGERU ES, SOUTHERN SUPPORT COMMAND ES, SANTA BARBARA CS, TOLOSA ES, BALIWASAN CS, CABATANGAN ES, PANGULAYAN ES, LANOTE ES, ET. AL.

CONSTRUCTION OF RAINWATER COLLECTOR SYSTEM AT LUMAYANG ES, MANGGA ES, CRISTINO M. PARAGAS ES, SAN JOSE GUSU ES, SHIGERU ES, SOUTHERN SUPPORT COMMAND ES, SANTA BARBARA CS, TOLOSA ES, BALIWASAN CS, CABATANGAN ES, PANGULAYAN ES, LANOTE ES, ET. AL. is a DPWH-tracked public work in Zamboanga City 2nd DEO, Region IX. Reported contract value: ₱3,626,230.68. Status: Reported complete (DPWH). Contractor on record: VAF CONST 34593. Figures trace to dpwh.

Zamboanga City 2nd DEO, Region IX
Region: Region IX

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2019 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱3,626,230.68

Progress

Reported complete (DPWH)

Start Date

September 30, 2019

Target End

December 28, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.