Flood Control and Drainage20AJ0030

CONSTRUCTION OF DRAINAGE STRUCTURE, BRGY. CALOMBOYAN, SAN CARLOS CITY, PANGASINAN

CONSTRUCTION OF DRAINAGE STRUCTURE, BRGY. CALOMBOYAN, SAN CARLOS CITY, PANGASINAN is a DPWH-tracked public work in Pangasinan 4th DEO, Region I. Reported contract value: ₱2,878,973.81. Status: Reported complete (DPWH). Contractor on record: J C FERRER CONST. Figures trace to dpwh.

Pangasinan 4th DEO, Region I
Region: Region I

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱2,878,973.81

Progress

Reported complete (DPWH)

Start Date

February 14, 2020

Target End

July 14, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.