Construction of Flood Mitigation Structure22IF0003

Construction of Tabunok Flood Control, Isabel, Leyte

Construction of Tabunok Flood Control, Isabel, Leyte is a DPWH-tracked public work in ISABEL (LEYTE), LEYTE, Region VIII. Reported contract value: ₱19,599,997.66. Status: Reported complete (DPWH). Contractor on record: CLMB CONST. Figures trace to sumbong.

ISABEL (LEYTE), LEYTE, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Tabunok Flood Control, Isabel, Leyte
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002766

₱458,000,000.00 · FY2022

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱19,599,997.66

Progress

Reported complete (DPWH)

Start Date

February 21, 2022

Target End

July 20, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.