Flood Control and Drainage24CL0025

CONSTRUCTION OF SLOPE PROTECTION ALONG BUCAO RIVER, DOWNSTREAM, NORTH APPROACH, BOTOLAN, ZAMBALES, PHASE II

CONSTRUCTION OF SLOPE PROTECTION ALONG BUCAO RIVER, DOWNSTREAM, NORTH APPROACH, BOTOLAN, ZAMBALES, PHASE II is a DPWH-tracked public work in Zambales 1st DEO, Region III. Reported contract value: ₱96,497,921.18. Status: Past target date (DPWH On-Going). Contractor on record: ELITE GEN CONTRACTOR AND DEVELOPMENT CORP. Figures trace to dpwh.

Zambales 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control / Slope Protection Works along Sto. Niño Creek, Capayawan, Botolan, Zambales
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Zambales 1st DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

121 projects · ₱7.5B total · 3 flags

Other projects by this contractor

Construction of Road Dike along Bucayao River (East Side), Sitio Malinao Section, Barangay Tagumpay, Naujan, Oriental Mindoro

NAUJAN (ORIENTAL MINDORO), ORIENTAL MINDORO, Region IV-B

2024₱247.5M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG BUSUANGA RIVER, BRGY. SAN PEDRO (DOWNSTREAM), SAN JOSE, OC

Region IV-B, Region IV-B

2024₱232.4M
Past target date (DPWH On-Going)
No sat.

OO 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONST./ REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF LOBOC RIVER CONTROL STRUCTURE, VILLAFLOR SECTION, LOBOC, BOHOL

Region VII, Region VII

2023₱213.9M
Past target date (DPWH On-Going)
No sat.

OO 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONST./ REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF LOBOC RIVER CONTROL STRUCTURE, CANLASID SECTION, LOBOC, BOHOL

Region VII, Region VII

2023₱193.0M
Past target date (DPWH On-Going)

Construction of Road Dike along Mag-asawang Tubig River, Sitio Dike, Barangay Apitong Section, Naujan, Oriental Mindoro

NAUJAN (ORIENTAL MINDORO), ORIENTAL MINDORO, Region IV-B

2024₱193.0M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY HINOLASO, DOLORES, EASTERN SAMAR

Region VIII, Region VIII

2024₱190.9M
Past target date (DPWH On-Going)
View all 121 projects →

4. Implementation

Contract Amount

₱96,497,921.18

Progress

Past target date (DPWH On-Going)

Start Date

February 16, 2024

Target End

April 10, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.