Flood Control and Drainage18JF0005

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SIBUGUEY RIVER (PHASE VII) SIAY, ZAMBOANGA SIBUGAY, SIAY, ZAMBOANGA SIBUGAY

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SIBUGUEY RIVER (PHASE VII) SIAY, ZAMBOANGA SIBUGAY, SIAY, ZAMBOANGA SIBUGAY is a DPWH-tracked public work in Zamboanga Sibugay 2nd DEO, Region IX. Reported contract value: ₱42,518,086.67. Status: Reported complete (DPWH). Contractor on record: RUDHIL CONST. Figures trace to dpwh.

Zamboanga Sibugay 2nd DEO, Region IX
Region: Region IX

Money Trail

1. Appropriation

Probable match · score 95%

UACS
18001
Amount
₱45,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Sibuguey River (Phase VII), Siay, Zamboanga Sibugay
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Agency-level releases for FY2018, not tied to this contract

Zamboanga Sibugay 2nd DEO · SARO 1,489 (₱126,676,811,675.00) · NCA 1,617 (₱426,584,627,343.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱42,518,086.67

Progress

Reported complete (DPWH)

Start Date

March 20, 2018

Target End

February 7, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.