Roads19EA0029

NETWORK DEVELOPMENT- ROAD WIDENING-SECONDARY ROADS, MOGPOG-BALANACAN PORT ROAD-K0011+600-K0012+600

NETWORK DEVELOPMENT- ROAD WIDENING-SECONDARY ROADS, MOGPOG-BALANACAN PORT ROAD-K0011+600-K0012+600 is a DPWH-tracked public work in Marinduque DEO, Region IV-B. Reported contract value: ₱25,999,389.58. Status: Reported complete (DPWH). Contractor on record: MONOLITHIC CONST. Figures trace to dpwh.

Marinduque DEO, Region IV-B
Region: Region IV-B

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2019 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱25,999,389.58

Progress

Reported complete (DPWH)

Start Date

June 10, 2019

Target End

June 15, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.