Buildings and Facilities15FF0092

CLUSTER-VII (FY-2016 INFRASTRUCTURE-LOCAL INFRA. PROGRAM/CONSTRUCTION OF MULTI-PURPOSE BUILDING) LAGONOY AND PRESENTACION, CAMARINES SUR

CLUSTER-VII (FY-2016 INFRASTRUCTURE-LOCAL INFRA. PROGRAM/CONSTRUCTION OF MULTI-PURPOSE BUILDING) LAGONOY AND PRESENTACION, CAMARINES SUR is a DPWH-tracked public work in Camarines Sur 4th DEO, Region V. Reported contract value: ₱4,872,962.96. Status: Reported complete (DPWH). Contractor on record: BUILDWAYS CONST. Figures trace to dpwh.

Camarines Sur 4th DEO, Region V
Region: Region V

Money Trail

1. Appropriation

GAA FY2016 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱4,872,962.96

Progress

Reported complete (DPWH)

Start Date

February 25, 2016

Target End

May 24, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.