WIDENING OF BRIDGE APPROACH AND CAUSEWAY IMPROVEMENT OF BRIDGE APPROACH CAUSEWAY ALONG NATIONAL ROAD, SIMUNUL CIRCUMFERENTIAL NATIONAL ROAD, TAWI TAWI, STA. 14+844.00 TO STA. 15+002, NET LENGTH: 158.00 LN.M.
WIDENING OF BRIDGE APPROACH AND CAUSEWAY IMPROVEMENT OF BRIDGE APPROACH CAUSEWAY ALONG NATIONAL ROAD, SIMUNUL CIRCUMFERENTIAL NATIONAL ROAD, TAWI TAWI, STA. 14+844.00 TO STA. 15+002, NET LENGTH: 158.00 LN.M. is a DPWH-tracked public work in Region IX, Region IX. Reported contract value: ₱37,236,785.50. Status: Reported complete (DPWH). Contractor on record: FFJJ CONST 16712. Figures trace to dpwh.
Total Contract Cost