Buildings and Facilities19JF0032

CONSTRUCTION OF COVERED COURT, BRGY. PALOMOC, MUNICIPALITY OF TITAY, ZAMBOANGA SIBUGAY

CONSTRUCTION OF COVERED COURT, BRGY. PALOMOC, MUNICIPALITY OF TITAY, ZAMBOANGA SIBUGAY is a DPWH-tracked public work in Zamboanga Sibugay 2nd DEO, Region IX. Reported contract value: ₱1,971,243.80. Status: Reported complete (DPWH). Contractor on record: SQUARE ONE BUILDERS. Figures trace to dpwh.

Zamboanga Sibugay 2nd DEO, Region IX
Region: Region IX

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIX-19-0025380

₱476,000.00 · FY2019

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

41 projects · ₱152.9M total · 0 flags

4. Implementation

Contract Amount

₱1,971,243.80

Progress

Reported complete (DPWH)

Start Date

June 25, 2019

Target End

August 23, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.