Roads18GB0047

CONSTRUCTION OF BYPASS ROAD: HAMTIC-SAN JOSE-SIBALOM BYPASS ROAD INCLUDING ROW, ANTIQUE

CONSTRUCTION OF BYPASS ROAD: HAMTIC-SAN JOSE-SIBALOM BYPASS ROAD INCLUDING ROW, ANTIQUE is a DPWH-tracked public work in Antique DEO, Region VI. Reported contract value: ₱22,703,549.54. Status: Reported complete (DPWH). Contractor on record: ROAD EDGE TRADING. Figures trace to dpwh.

Antique DEO, Region VI
Region: Region VI

Money Trail

1. Appropriation

GAA FY2018 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

223 projects · ₱12.5B total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD CONTROL MITIGATION STRUCTURE, BARANGAY GUINACUTAN, VINZ

Region V, Region V

2025₱144.9M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD CONTROL MITIGATION STRUCTURE ALONG CULASI, BARANGAY PAM

Region V, Region V

2025₱144.9M
Past target date (DPWH On-Going)

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG AGUIBAWA RIVER, BANTACAN, NEW BATAAN, DAVAO DE ORO

Davao de Oro 2nd DEO, Region XI

2024₱144.7M
Reported complete (DPWH)
No sat.

REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE ALONG PORT BARTON-TDC ROAD SECTION, STA. 017+770-STA. 017+865; STA. 017+914-STA. 017+969; STA. 018+023-STA. 018+244, PALAWAN

Region IV-B, Region IV-B

2022₱144.5M
Reported complete (DPWH)
No sat.

REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - PRIMARY ROADS - BUTUAN CITY-CAGAYAN DE ORO CITY-ILIGAN CITY RD - K1398 + 300- K1398 + 600

Misamis Oriental 1st DEO, Region X

2025₱143.3M
Past target date (DPWH On-Going)
No sat.

REHABILITATION OF DRAINAGE SYSTEM ALONG DAGUPAN ST., MANILA CITY, PHASE 1

North Manila DEO, National Capital Region

2025₱140.3M
Past target date (DPWH On-Going)
View all 223 projects →

4. Implementation

Contract Amount

₱22,703,549.54

Progress

Reported complete (DPWH)

Start Date

May 22, 2018

Target End

September 21, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.