Flood Control and Drainage20CD0037

CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG MARILAO RIVER AND ITS TRIBUTARIES PHASE III, MARILAO, BULACAN

CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG MARILAO RIVER AND ITS TRIBUTARIES PHASE III, MARILAO, BULACAN is a DPWH-tracked public work in Bulacan 2nd DEO, Region III. Reported contract value: ₱45,812,896.05. Status: Reported complete (DPWH). Contractor on record: S A PLEYTO CONST CORP. Figures trace to dpwh.

Bulacan 2nd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 97%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures along Marilao River and its tributaries Phase III, Marilao, Bulacan
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Bulacan 2nd DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

4. Implementation

Contract Amount

₱45,812,896.05

Progress

Reported complete (DPWH)

Start Date

February 17, 2020

Target End

November 8, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.