Flood Control and Drainage15AI0444

CONST/MAINT OF FLOOD MITIGATION STRUCTURES & DRAINAGE SYSTEM-CONST OF CROSS DRAIN, MNR, BRGY. BUED,

CONST/MAINT OF FLOOD MITIGATION STRUCTURES & DRAINAGE SYSTEM-CONST OF CROSS DRAIN, MNR, BRGY. BUED, is a DPWH-tracked public work in Pangasinan 3rd DEO, Region I. Reported contract value: ₱2,856,179.77. Status: Past target date (DPWH On-Going). Contractor on record: MKM MARKETING. Figures trace to dpwh.

Pangasinan 3rd DEO, Region I
Region: Region I

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2016 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱2,856,179.77

Progress

Past target date (DPWH On-Going)

Start Date

March 6, 2016

Target End

May 25, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.