Roads24CL0102

ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE-TERTIARY ROADS-SN MARCELINO-SN ANTONIO-SN NARCISO RD-K0162+407.72-K0163+000,K0164+000-K0164+404,K0165+000-K0165+705, K0166+286-K0166+639, SAN ANTONIO & SAN NARCISO, ZAMBALES

ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE-TERTIARY ROADS-SN MARCELINO-SN ANTONIO-SN NARCISO RD-K0162+407.72-K0163+000,K0164+000-K0164+404,K0165+000-K0165+705, K0166+286-K0166+639, SAN ANTONIO & SAN NARCISO, ZAMBALES is a DPWH-tracked public work in Zambales 1st DEO, Region III. Reported contract value: ₱96,474,523.24. Status: Past target date (DPWH On-Going). Contractor on record: ORIENTAL SALES CENTER AND CONTRACTOR. Figures trace to dpwh.

Zambales 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Omaya River, San Narciso, Zambales ( Phase 1 )
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Zambales 1st DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱96,474,523.24

Progress

Past target date (DPWH On-Going)

Start Date

February 15, 2024

Target End

August 7, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.