Construction of Flood Mitigation Structure21EI0128

Construction of Baroc River Control, Roma Section, Mansalay, Oriental Mindoro

Construction of Baroc River Control, Roma Section, Mansalay, Oriental Mindoro is a DPWH-tracked public work in ORIENTAL MINDORO, Region IV-B. Reported contract value: ₱19,599,948.04. Status: Reported complete (DPWH). Contractor on record: D M MALIWANAG BUILDERS AND ENT. Figures trace to sumbong.

ORIENTAL MINDORO, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱2,861,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure in Bongabong River, Mapang Section, Bongabong, Oriental Mindoro
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0013848

₱10,500,000.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0014159

₱10,000,000.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0007558

₱4,000,000.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-21-0012678

₱1,446,015.00 · FY2021

Source

3. Procurement & Award

Confirmed (exact contract ID) · 100%

21EI0128 - Construction of Baroc River Control, Ro

₱18,815,088.38 · D.M. MALIWANAG BUILDERS AND ENTERPRISES

4. Implementation

Contract Amount

₱19,599,948.04

Progress

Reported complete (DPWH)

Start Date

April 8, 2022

Target End

October 14, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.