Roads22FO0053

CONSTRUCTION OF TINAGO/MAHABA BUSAY ROAD (PHASE 2), BARANGAY MAHABA TO BARANGAY BUSAY, LIGAO CITY, ALBAY

CONSTRUCTION OF TINAGO/MAHABA BUSAY ROAD (PHASE 2), BARANGAY MAHABA TO BARANGAY BUSAY, LIGAO CITY, ALBAY is a DPWH-tracked public work in Albay 3rd DEO, Region V. Reported contract value: ₱25,733,445.81. Status: Past target date (DPWH On-Going). Contractor on record: 4DOVE BUILDERS CORP 36232. Figures trace to dpwh.

Albay 3rd DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control/River Dike, Barangay Pandan, Ligao City, Albay
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Albay 3rd DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 36232

53 projects · ₱708.7M total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM - CONSTRUCTION OF CABILOGAN RIVER FLOOD MITIGATION STRUCTURE, BARANGAY B

Albay 3rd DEO, Region V

2024₱112.3M
Past target date (DPWH On-Going)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF SAN VICENTE-OBALIW RIÑAS ROAD, OAS, ALBAY

Albay 3rd DEO, Region V

2023₱49.4M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM- SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONCRETING OF MAHABA-BUSAY ROAD IN LIGA

Albay 3rd DEO, Region V

2024₱47.7M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONCRETING OF DUNAO-BONGA-PAULOG ROAD

Albay 3rd DEO, Region V

2024₱40.0M
Past target date (DPWH On-Going)
No sat.

CONCRETING OF BRGY. BINATAGAN FMR, BRGY. BINATAGAN, LIGAO CITY, ALBAY

Albay 3rd DEO, Region V

2024₱29.1M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF ROAD, DUNAO (SAN ROQUE ST.) TO BARANGAY BONGA, LIGAO CITY, ALBAY

Albay 3rd DEO, Region V

2021₱25.5M
Reported complete (DPWH)
View all 53 projects →

4. Implementation

Contract Amount

₱25,733,445.81

Progress

Past target date (DPWH On-Going)

Start Date

February 21, 2022

Target End

August 4, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.