Flood Control and Drainage18CE0022

CONSTRUCTION/REHABILITATION OF FLOOD CONTROL STRUCTURES, BRGY. BACAYAO, GUIMBA, NUEVA ECIJA

CONSTRUCTION/REHABILITATION OF FLOOD CONTROL STRUCTURES, BRGY. BACAYAO, GUIMBA, NUEVA ECIJA is a DPWH-tracked public work in Nueva Ecija 1st DEO, Region III. Reported contract value: ₱18,617,041.44. Status: Reported complete (DPWH). Contractor on record: L S D CONST. Figures trace to dpwh.

Nueva Ecija 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

GAA FY2018 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱18,617,041.44

Progress

Reported complete (DPWH)

Start Date

July 8, 2018

Target End

December 4, 2018

5. Audit