Buildings and Facilities18GJ0161

CONSTRUCTION/UPGRADING OF HEALTH CENTER JARO IB, MAIN HEALTH CENTER

CONSTRUCTION/UPGRADING OF HEALTH CENTER JARO IB, MAIN HEALTH CENTER is a DPWH-tracked public work in Iloilo City DEO, Region VI. Reported contract value: ₱6,477,504.92. Status: Reported complete (DPWH). Contractor on record: G F FALCIS CONST. Figures trace to dpwh.

Iloilo City DEO, Region VI
Region: Region VI

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱45,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Revetment Wall at Dungon Creek Section 1 ( Brgy. Dungon A, Jaro - Brgy. Sta. Rosa, Mandurriao) Iloilo City
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Agency-level releases for FY2018, not tied to this contract

Iloilo City DEO · SARO 1,489 (₱126,676,811,675.00) · NCA 1,617 (₱426,584,627,343.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱6,477,504.92

Progress

Reported complete (DPWH)

Start Date

February 18, 2020

Target End

October 8, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.