Roads25DC0004

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, ROAD WIDENING - SECONDARY ROADS, PALICO-BALAYAN-BATANGAS RD

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, ROAD WIDENING - SECONDARY ROADS, PALICO-BALAYAN-BATANGAS RD is a DPWH-tracked public work in Batangas 3rd DEO, Region IV-A. Reported contract value: ₱38,215,602.00. Status: Past target date (DPWH On-Going). Contractor on record: VAN MAKJAY CONST 50686. Figures trace to dpwh.

Batangas 3rd DEO, Region IV-A
Region: Region IV-A

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure in Taal, Batangas
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Batangas 3rd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 50686

27 projects · ₱248.1M total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - SECONDARY ROADS, PALICO - BALAYAN - BATANGAS RD

Batangas 3rd DEO, Region IV-A

2024₱68.0M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM -TRIP), TAAL LAKE CIRCUMFERENTIAL ROAD (AGONCILLO SECTION), AGONCILLO, BATANGAS

Batangas 3rd DEO, Region IV-A

2025₱16.7M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF ELEMENTARY AND SECONDARY CLASSROOMS (BATCH 1) UNDER THE DEPED'S CY 2023 BASIC EDUCATION FACILITIES FUND, CONSTRUCTION OF 2STYCL, CORAL NA MUNTI NATIONAL HIGH SCHOOL, AGONCILLO, BATANGAS

Batangas 3rd DEO, Region IV-A

2023₱15.0M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP), BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BRGY. POBLACION, SAN NICOLAS, BATANGAS

Batangas 3rd DEO, Region IV-A

2024₱14.8M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP), BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, REHABILITATION OF MULTI-PURPOSE BUILDING, BRGY. POBLACION, SAN NICOLAS, BATANGAS

Batangas 3rd DEO, Region IV-A

2024₱9.9M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, COMPLETION OF MULTI-PURPOSE BUILDING IN THE MUNICIPALITY OF AGONCILLO, BATANGAS

Batangas 3rd DEO, Region IV-A

2022₱5.9M
Reported complete (DPWH)
View all 27 projects →

4. Implementation

Contract Amount

₱38,215,602.00

Progress

Past target date (DPWH On-Going)

Start Date

March 27, 2025

Target End

August 23, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.