Buildings and Facilities19LB0090

CONSTRUCTION (COMPLETION) OF MPB, BRGY. BAGO GALLERA, DAVAO CITY

CONSTRUCTION (COMPLETION) OF MPB, BRGY. BAGO GALLERA, DAVAO CITY is a DPWH-tracked public work in Davao City DEO, Region XI. Reported contract value: ₱2,895,750.06. Status: Reported complete (DPWH). Contractor on record: H-ROYAL CONST. Figures trace to dpwh.

Davao City DEO, Region XI
Region: Region XI

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱2,895,750.06

Progress

Reported complete (DPWH)

Start Date

July 18, 2019

Target End

October 15, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.