CONVERGENCE AND SPECIAL SUPPORT PROG BASIC INFRASTRUCTURE PROGRAM (BIP)BIP - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIESCONSTRUCTION OF REVETMENT ALONG YLANG-YLANG, SAN FRANCISCO, GEN. TRIAS, CAVITE (PHASE I)

CONVERGENCE AND SPECIAL SUPPORT PROG BASIC INFRASTRUCTURE PROGRAM (BIP)BIP - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIESCONSTRUCTION OF REVETMENT ALONG YLANG-YLANG, SAN FRANCISCO, GEN. TRIAS, CAVITE (PHASE I) is a DPWH-tracked public work in Cavite 1st DEO, Region IV-A. Reported contract value: ₱99,000,000.00. Status: Past target date (DPWH On-Going). Contractor on record: NEWBIG FOUR J CONST INC FORMERLY: FOUR J CONST 15104. Figures trace to dpwh.

Cavite 1st DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱36,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure and Other Improvements, Brgy. Molino 6 to Brgy. San Nicolas 3, Bacoor, Cavite
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Cavite 1st DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

4. Implementation

Contract Amount

₱99,000,000.00

Progress

Past target date (DPWH On-Going)

Start Date

April 17, 2024

Target End

March 19, 2025