Roads22PE0035

REHABILITATION/MAJOR REPAIR OF DRAINAGE STRUCTURE ALONG ROAD - TAWANG-AMBIONG ROAD (S00387LZ)- K0260+(-193), K0260+018, K0260+250, K0260+497, K0260+518, K0260+918, K0261+042, K0261+409, K0261+958, K0262+900, K0263+090, K0264+175-K0264+245, K0264+552, LA T

REHABILITATION/MAJOR REPAIR OF DRAINAGE STRUCTURE ALONG ROAD - TAWANG-AMBIONG ROAD (S00387LZ)- K0260+(-193), K0260+018, K0260+250, K0260+497, K0260+518, K0260+918, K0261+042, K0261+409, K0261+958, K0262+900, K0263+090, K0264+175-K0264+245, K0264+552, LA T is a DPWH-tracked public work in Benguet 1st DEO, Cordillera Administrative Region. Reported contract value: ₱19,500,067.70. Status: Reported complete (DPWH). Contractor on record: SHIKIFUJIN BUILDERS OPC. Figures trace to dpwh.

Benguet 1st DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure within Agno River Basin: along Agno River Section 20 (Ekip), Bokod, Benguet
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Benguet 1st DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

4. Implementation

Contract Amount

₱19,500,067.70

Progress

Reported complete (DPWH)

Start Date

May 10, 2022

Target End

November 1, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.