Roads24K00050

CONSTRUCTION OF MISSING LINKS/NEW ROADS, JCT. CDO CITY CAMP KIBARITAN-DOMINOROG ROAD TO JCT. MANOLO FORTICH LIBONA-INDAHAG ROAD(TUMALAONG BRIDGE), BUKIDNON

CONSTRUCTION OF MISSING LINKS/NEW ROADS, JCT. CDO CITY CAMP KIBARITAN-DOMINOROG ROAD TO JCT. MANOLO FORTICH LIBONA-INDAHAG ROAD(TUMALAONG BRIDGE), BUKIDNON is a DPWH-tracked public work in Region X, Region X. Reported contract value: ₱11,422,271.04. Status: Reported complete (DPWH). Contractor on record: RAMISES CONST. Figures trace to dpwh.

Region X, Region X
Region: Region X

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2024 GAA. DBM GAA FY2024

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱11,422,271.04

Progress

Reported complete (DPWH)

Start Date

March 4, 2024

Target End

February 26, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.