Flood Control and Drainage19AC0029

CONSTRUCTION OF FLOOD CONTROL ALONG ABRA RIVER (PHASE II), VIGAN CITY, ILOCOS SUR

CONSTRUCTION OF FLOOD CONTROL ALONG ABRA RIVER (PHASE II), VIGAN CITY, ILOCOS SUR is a DPWH-tracked public work in Ilocos Sur 1st DEO, Region I. Reported contract value: ₱18,631,749.83. Status: Reported complete (DPWH). Contractor on record: 739 BUILDERS. Figures trace to dpwh.

Ilocos Sur 1st DEO, Region I
Region: Region I

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-LGRCB-19-0003441

₱2,100,000.00 · FY2019

Released to Central Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

623 projects · ₱14.3B total · 27 flags

4. Implementation

Contract Amount

₱18,631,749.83

Progress

Reported complete (DPWH)

Start Date

July 10, 2019

Target End

January 25, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.