Flood Control and Drainage21GL0029

CONSTRUCTION OF BINALBAGAN RIVER BANK SLOPE PROTECTION (UPSTREAM OF ALICANTE BRIDGE) ALONG JCT BAGONAWA - LA CASTELLANA - ISABELA ROAD, (RIGHT BANK), NEGROS OCCIDENTAL

CONSTRUCTION OF BINALBAGAN RIVER BANK SLOPE PROTECTION (UPSTREAM OF ALICANTE BRIDGE) ALONG JCT BAGONAWA - LA CASTELLANA - ISABELA ROAD, (RIGHT BANK), NEGROS OCCIDENTAL is a DPWH-tracked public work in Negros Occidental 2nd DEO, Negros Island Region. Reported contract value: ₱71,344,380.00. Status: Reported complete (DPWH). Contractor on record: JAIME B CHING ENT 4256. Figures trace to dpwh.

Negros Occidental 2nd DEO, Negros Island Region
Region: Negros Island Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱45,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure of Bagacay River along Bacolod Silay Airport Access Road, Silay City, Negros Occidental
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Negros Occidental 2nd DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱71,344,380.00

Progress

Reported complete (DPWH)

Start Date

April 12, 2021

Target End

January 7, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.