Roads24D00122

DAANG MAHARLIKA (LZ) K0140 + 120 - K0140 + 140, K0142 + 200 - K0142 + 300, K0142 + 945 - K0143 + 306, K0143 + 367 - K0143 + 474, K0145 + 004 - K0145 + 165, K0145 + 300 - K0145 + 325, K0145 + 447 - K0145 + 564, K0146 + 762 - K0147 + 190, K0147 + 600 - K014

DAANG MAHARLIKA (LZ) K0140 + 120 - K0140 + 140, K0142 + 200 - K0142 + 300, K0142 + 945 - K0143 + 306, K0143 + 367 - K0143 + 474, K0145 + 004 - K0145 + 165, K0145 + 300 - K0145 + 325, K0145 + 447 - K0145 + 564, K0146 + 762 - K0147 + 190, K0147 + 600 - K014 is a DPWH-tracked public work in Region IV-A, Region IV-A. Reported contract value: ₱167,900,733.09. Status: Past target date (DPWH On-Going). Contractor on record: NEWBIG FOUR J CONST INC FORMERLY: FOUR J CONST. Figures trace to dpwh.

Region IV-A, Region IV-A
Region: Region IV-A

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱167,900,733.09

Progress

Past target date (DPWH On-Going)

Start Date

October 23, 2024

Target End

August 18, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.