Flood Control and Drainage21KJ0027

CONSTRUCTION OF BRGY. VILLA CONSUELO PHASE 2, OZAMIZ CITY

CONSTRUCTION OF BRGY. VILLA CONSUELO PHASE 2, OZAMIZ CITY is a DPWH-tracked public work in Misamis Occidental 2nd DEO, Region X. Reported contract value: ₱11,429,294.56. Status: Reported complete (DPWH). Contractor on record: RJLG CONST AND SUPPLIES. Figures trace to dpwh.

Misamis Occidental 2nd DEO, Region X
Region: Region X

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱70,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Baybay-Migpangi Flood Control, Bonifacio, Misamis Occidental
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Misamis Occidental 2nd DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱11,429,294.56

Progress

Reported complete (DPWH)

Start Date

December 3, 2021

Target End

May 12, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.