Flood Control and Drainage24GN0069

CONSTRUCTION OF SHORELINE PROTECTION ALONG GUIMARAS STRAIT, BRGY. UTOD, PULUPANDAN, NEGROS OCCIDENTAL (PHASE I)

CONSTRUCTION OF SHORELINE PROTECTION ALONG GUIMARAS STRAIT, BRGY. UTOD, PULUPANDAN, NEGROS OCCIDENTAL (PHASE I) is a DPWH-tracked public work in Negros Occidental 4th DEO, Negros Island Region. Reported contract value: ₱49,004,837.02. Status: Reported complete (DPWH). Contractor on record: GROUND UP CONST AND SUPPLIES 42322. Figures trace to dpwh.

Negros Occidental 4th DEO, Negros Island Region
Region: Negros Island Region

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Patic Creek ( Phase 4 ) , Barangay Patic, Pulupandan, Negros Occidental
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Negros Occidental 4th DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱49,004,837.02

Progress

Reported complete (DPWH)

Start Date

April 11, 2024

Target End

October 21, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.