Flood Control and Drainage19PL0079

CONSTRUCTION OF FLOOD CONTROL AT DAGUPAN CENTRO MARKET SECTION, BRGY. DAGUPAN CENTRO, TABUK CITY, KALINGA

CONSTRUCTION OF FLOOD CONTROL AT DAGUPAN CENTRO MARKET SECTION, BRGY. DAGUPAN CENTRO, TABUK CITY, KALINGA is a DPWH-tracked public work in Lower Kalinga DEO, Cordillera Administrative Region. Reported contract value: ₱1,255,785.65. Status: Reported complete (DPWH). Contractor on record: MATAGOAN KJ BUILDERS AND ENGINEERING SERVICES. Figures trace to dpwh.

Lower Kalinga DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROIII-19-0011575

₱229,674.00 · FY2019

Released to al Wo Baler National High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

38 projects · ₱158.2M total · 0 flags

Other projects by this contractor

No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP) - INTERJURISDICTIONAL ROADS AND/OR BRIDGES (OR, ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS) - CONSTRUCTION OF MANGBA ROAD LEADING TO LGU PABAHAY ROAD, BARANGAY BALONG, TABUK CITY, KALINGA

Lower Kalinga DEO, Cordillera Administrative Region

2023₱29.6M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS: FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS: CONSTRUCTION OF JANOM SISIM FLOOD CONTROL STA. 179+550 - STA. 179+310 (R.

Upper Kalinga DEO, Cordillera Administrative Region

2021₱9.8M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS: FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS: CONSTRUCTION OF CHINA-AW FLOOD CONTROL STA. 170+790 - 170+970 (R.S.), BAL

Upper Kalinga DEO, Cordillera Administrative Region

2021₱9.7M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS: FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS: CONSTRUCTION OF LINAS-SAYANGAN CREEK FLOOD CONTROL STA. 173+790 - STA. 17

Upper Kalinga DEO, Cordillera Administrative Region

2021₱9.0M
Reported complete (DPWH)
No sat.

Construction of Yakyak Mabilong - Malusong Flood Control Structure, Sta. 170+200 - Sta. 170+275 (B.S.), Mabilong and Antonio Canao, Lubuagan, Kalinga

LUBUAGAN (KALINGA), KALINGA, Cordillera Administrative Region

2022₱8.4M
Reported complete (DPWH)
No sat.

ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE SECONDARY ROADS - MT. PROVINCE BOUNDARY-CALANAN-PINUKPUK-ABBUT ROAD (PINUKPUK-ABBUT SECTION), K0523+856-K0523+936, K0528+982-K0528+997, K0529+048-

Lower Kalinga DEO, Cordillera Administrative Region

2020₱6.4M
Reported complete (DPWH)
View all 38 projects →

4. Implementation

Contract Amount

₱1,255,785.65

Progress

Reported complete (DPWH)

Start Date

July 11, 2019

Target End

August 9, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.