Flood Control and Drainage20GI0015

CONSTRUCTION OF SIBALOM FLOOD CONTROL PROJECT (SIBALOM RIVER), BRGY.LANAG, LEON, ILOILO

CONSTRUCTION OF SIBALOM FLOOD CONTROL PROJECT (SIBALOM RIVER), BRGY.LANAG, LEON, ILOILO is a DPWH-tracked public work in Iloilo 4th DEO, Region VI. Reported contract value: ₱55,493,227.94. Status: Reported complete (DPWH). Contractor on record: IBC INTERNATIONAL BUILDERS CORP 8576. Figures trace to dpwh.

Iloilo 4th DEO, Region VI
Region: Region VI

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱55,493,227.94

Progress

Reported complete (DPWH)

Start Date

February 26, 2020

Target End

October 21, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.