Roads16PC0025

CONCRETING OF DONA LORETA-PIPIIG-POBLACION FMR, PUDTOL, APAYAO

CONCRETING OF DONA LORETA-PIPIIG-POBLACION FMR, PUDTOL, APAYAO is a DPWH-tracked public work in Apayao 2nd DEO, Cordillera Administrative Region. Reported contract value: ₱2,967,199.71. Status: Reported complete (DPWH). Contractor on record: W J P CONST AND SUPPLY 23192. Figures trace to dpwh.

Apayao 2nd DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

GAA FY2016 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱2,967,199.71

Progress

Reported complete (DPWH)

Start Date

October 25, 2016

Target End

February 5, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.