Flood Control and Drainage19N00019

CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD MITIGATION STRUCTURES- LOWER AGUSAN DEVELOPMENT PROJECT, FLOOD CONTROL COMPONENT, STAGE 1, PHASE II, EAST BANK DRAINAGE, AMPAYON, BUTUAN CITY

CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD MITIGATION STRUCTURES- LOWER AGUSAN DEVELOPMENT PROJECT, FLOOD CONTROL COMPONENT, STAGE 1, PHASE II, EAST BANK DRAINAGE, AMPAYON, BUTUAN CITY is a DPWH-tracked public work in Region XIII, Region XIII. Reported contract value: ₱106,149,983.85. Status: Reported complete (DPWH). Contractor on record: ADFIL CORP. Figures trace to dpwh.

Region XIII, Region XIII
Region: Region XIII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱106,149,983.85

Progress

Reported complete (DPWH)

Start Date

July 15, 2019

Target End

March 23, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.