Buildings and Facilities17FC0139

CONST. OF ONE (1) STOREY TWO (2) CLASSROOM SCHOOL BLDG., G. CALE ELEM. SCHOOL, LABO CAMS. NORTE

CONST. OF ONE (1) STOREY TWO (2) CLASSROOM SCHOOL BLDG., G. CALE ELEM. SCHOOL, LABO CAMS. NORTE is a DPWH-tracked public work in Camarines Norte DEO, Region V. Reported contract value: ₱2,605,947.21. Status: Reported complete (DPWH). Contractor on record: BRENTMIN ROOFING ENT 37191. Figures trace to dpwh.

Camarines Norte DEO, Region V
Region: Region V

Money Trail

1. Appropriation

GAA FY2017 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 37191

217 projects · ₱6.8B total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-BIP-FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, BARANGAY MOCONG, BASUD, CAMARINES NORTE, BASUD, C

Region V, Region V

2025₱240.1M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-BIP-FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, BASUD RIVER, BARANGAY MAMPILI, BASUD, CAMARINES N

Region V, Region V

2025₱240.1M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, BARANGAY MATOOGTOOG AND BARANGAY

Region V, Region V

2025₱234.0M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-SIPAG-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF BASUD-LANOT ROAD, MERCED

Region V, Region V

2024₱186.2M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF MITIGATION STRUCTURE ALONG CULASI RIVER, BARANGAY PAMBUHAN, M

Region V, Region V

2024₱176.9M
Past target date (DPWH On-Going)

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG

Region V, Region V

2024₱162.1M
Reported complete (DPWH)
View all 217 projects →

4. Implementation

Contract Amount

₱2,605,947.21

Progress

Reported complete (DPWH)

Start Date

December 3, 2017

Target End

February 25, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.