Roads19PE0002

REHABILITATION / RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE: CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE ALONG BENGUET - NUEVA VIZCAYA ROAD (S00382LZ), K0271+690 - K0271+725, ITOGON, BENGUET

REHABILITATION / RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE: CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE ALONG BENGUET - NUEVA VIZCAYA ROAD (S00382LZ), K0271+690 - K0271+725, ITOGON, BENGUET is a DPWH-tracked public work in Benguet 1st DEO, Cordillera Administrative Region. Reported contract value: ₱32,770,591.13. Status: Reported complete (DPWH). Contractor on record: F B BANTALES ENGINEERING CONST. Figures trace to dpwh.

Benguet 1st DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

82 projects · ₱3.5B total · 0 flags

Other projects by this contractor

No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF PUERTO PRINCESA WEST COASTAL BYPASS ROAD, BRGY. BACUNGAN-SIMPOCAN, PTO. PRINCESA CITY, PALAWAN

Region IV-B, Region IV-B

2023₱187.8M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM NETWORK DEVELOPMENT - CONSTRUCTION OF MISSING LINKS/NEW ROADS KAMOG JCT. - CALOT - PAPPA - BAGONG - BALLUAY - TUEL JCT. (SECTION 2 OF BLISTT OUTER RING CIRCUMFERENTIAL ROAD) INCL. ROW

Cordillera Administrative Region, Cordillera Administrative Region

2018₱137.0M
Reported complete (DPWH)
No sat.

CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO AIRPORTS, SEAPORTS, AND DECLARED TOURISM DESTINATIONS BALLAY-TABIO-TONOMAN-BULALACAO-TAWANGAN-LUSOD ROAD LEADING TO BULALACAO LAKES AND MT. TABEO, KABAYAN, BENGUET

Benguet 1st DEO, Cordillera Administrative Region

2017₱96.5M
Reported complete (DPWH)
No sat.

REHABILITATION/IMPROVEMENT OF MADEGNAK-AGSIMAO ROAD, TINEG, ABRA

Abra DEO, Cordillera Administrative Region

2018₱96.4M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF SLOPE PROTECTION STRUCTURE -BENGUET-NUEVA VIZCAYA ROAD, K0271+780 - 0271+824, ITOGON, BENGUET, BENGUET

Benguet 1st DEO, Cordillera Administrative Region

2018₱96.3M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF MISSING LINKS / NEW ROADS (ROAD OPENING), BESAO - TUBO (VIA TAMBOAN), ABRA

Abra DEO, Cordillera Administrative Region

2018₱96.2M
Reported complete (DPWH)
View all 82 projects →

4. Implementation

Contract Amount

₱32,770,591.13

Progress

Reported complete (DPWH)

Start Date

June 24, 2019

Target End

November 20, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.