Construction of Flood Mitigation Structure23A00254

Construction of Flood Control Structure along Sta. Maria River (Package 1) Sta. Maria, Ilocos Sur

Construction of Flood Control Structure along Sta. Maria River (Package 1) Sta. Maria, Ilocos Sur is a DPWH-tracked public work in SANTA MARIA (ILOCOS SUR), ILOCOS SUR, Region I. Reported contract value: ₱46,808,283.34. Status: Reported complete (DPWH). Contractor on record: MBB CONST AND SUPPLY FORMERLY: MBB CONST. Figures trace to sumbong.

SANTA MARIA (ILOCOS SUR), ILOCOS SUR, Region I
Region: Region I

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Sta. Maria River (Package 1) Sta. Maria, Ilocos Sur
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Ilocos Sur 2nd District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱46,808,283.34

Progress

Reported complete (DPWH)

Start Date

April 5, 2023

Target End

October 27, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.