Roads25DN0035

REHABILITATION OF ROAD, ANTIPOLO HILLS, BARANGAY SAN LUIS, ANTIPOLO CITY, RIZAL (SECOND DISTRICT)

REHABILITATION OF ROAD, ANTIPOLO HILLS, BARANGAY SAN LUIS, ANTIPOLO CITY, RIZAL (SECOND DISTRICT) is a DPWH-tracked public work in Rizal 1st DEO, Region IV-A. Reported contract value: ₱9,605,611.96. Status: Past target date (DPWH On-Going). Contractor on record: TOP KMC CONST AND SUPPLY CORP 51165. Figures trace to dpwh.

Rizal 1st DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Barangay San Roque, Antipolo City, Rizal
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Rizal 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

4. Implementation

Contract Amount

₱9,605,611.96

Progress

Past target date (DPWH On-Going)

Start Date

May 23, 2025

Target End

September 19, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.