Buildings and Facilities19PF0045

LOCAL INFRASTRUCTURE PROGRAM: COMPLETION/IMPROVEMENT OF PALINA MULTI-PURPOSE BUILDING (PHASE 2), KIBUNGAN, BENGUET

LOCAL INFRASTRUCTURE PROGRAM: COMPLETION/IMPROVEMENT OF PALINA MULTI-PURPOSE BUILDING (PHASE 2), KIBUNGAN, BENGUET is a DPWH-tracked public work in Benguet 2nd DEO, Cordillera Administrative Region. Reported contract value: ₱737,115.29. Status: Reported complete (DPWH). Contractor on record: APAKLO KIN CONST AND ENG'G SERVICES. Figures trace to dpwh.

Benguet 2nd DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

18 projects · ₱162.9M total · 0 flags

Other projects by this contractor

No sat.

REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - TERTIARY ROADS: GOV. BADO DANGWA NATIONAL RD K0349+680 - K0349+741, K0349+757 - K0349+800, K0350+702 - K0350+744, K0350+814 - K0350+835

Benguet 2nd DEO, Cordillera Administrative Region

2022₱28.7M
Reported complete (DPWH)
No sat.

REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS: GOV. BADO DANGWA NATIONAL RD-K0306+700-K0306+783, K0306+900 - K0306+925, K0310+246 - K0310+272, K0311+530 - K0311+610

Benguet 2nd DEO, Cordillera Administrative Region

2025₱26.7M
Past target date (DPWH On-Going)
No sat.

Construction of Ampusongan Flood Control, Phase II, Ampusongan, Bakun, Benguet

BAKUN (BENGUET), BENGUET, Cordillera Administrative Region

2022₱19.6M
Reported complete (DPWH)
No sat.

ASSET PRESERVATION PROGRAM REHABILITATION/RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SOIL COLLAPSE, AND LANDSLIDE TERTIARY ROADS GOV. BADO DANGWA ROAD, K0337+830 K0337+892, K0343+215 K0343+324, BAKUN, BENGUET

Benguet 2nd DEO, Cordillera Administrative Region

2020₱13.4M
Reported complete (DPWH)
No sat.

REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS: GOV. BADO DANGWA NATIONAL RD - K0346+330 - K0346+350, K0348+730 - K0348+750

Benguet 2nd DEO, Cordillera Administrative Region

2025₱12.3M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONSTRUCTION OF SOLAR WATER SYSTEM, BAKUN, BENGUET

Benguet 2nd DEO, Cordillera Administrative Region

2023₱9.8M
Reported complete (DPWH)
View all 18 projects →

4. Implementation

Contract Amount

₱737,115.29

Progress

Reported complete (DPWH)

Start Date

August 6, 2019

Target End

September 9, 2019

5. Audit