Roads25J00005

CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, NRJ SANGALI BY-PASS ROAD PACKAGE 4, ZAMBOANGA CITY

CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, NRJ SANGALI BY-PASS ROAD PACKAGE 4, ZAMBOANGA CITY is a DPWH-tracked public work in Region IX, Region IX. Reported contract value: ₱36,152,238.77. Status: Past target date (DPWH On-Going). Contractor on record: HHH DEVELOPER AND CONST 37044. Figures trace to dpwh.

Region IX, Region IX
Region: Region IX

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱36,152,238.77

Progress

Past target date (DPWH On-Going)

Start Date

March 3, 2025

Target End

August 2, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.