Roads19DL0210

A. REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE ALONG LOPEZ-CATANAUAN RD K0226+280 - K0226+316, LOPEZ, QUEZONB. REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE ALONG LOPEZ-CATANAUAN RD K

A. REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE ALONG LOPEZ-CATANAUAN RD K0226+280 - K0226+316, LOPEZ, QUEZONB. REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE ALONG LOPEZ-CATANAUAN RD K is a DPWH-tracked public work in Quezon 4th DEO, Region IV-A. Reported contract value: ₱9,434,776.41. Status: Reported complete (DPWH). Contractor on record: R A MENDIOLA CONST. Figures trace to dpwh.

Quezon 4th DEO, Region IV-A
Region: Region IV-A

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

467 projects · ₱8.0B total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES 14. CONSTRUCTION OF ROAD, GUMACA, QUEZON,

Quezon 4th DEO, Region IV-A

2023₱106.2M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES 18. CONSTRUCTION/IMPROVEMENT OF ACCESS ROAD

Quezon 4th DEO, Region IV-A

2023₱106.2M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES 15. CONSTRUCTION/IMPROVEMENT OF ACCESS ROA

Quezon 4th DEO, Region IV-A

2023₱106.2M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES 16. CONSTRUCTION OF ROAD, GUINAYANGAN, QUE

Quezon 4th DEO, Region IV-A

2023₱106.2M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF FLOOD CONTROL, BARANGAY 1 AND BARANGAY 5, CATANAUAN, QUEZON

Quezon 3rd DEO, Region IV-A

2024₱101.7M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM, ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES 7. CONSTRUCTION OF LOPEZ -MACALELON ROAD, PACKAGE E, LOPEZ, QUEZON

Quezon 4th DEO, Region IV-A

2023₱99.0M
Reported complete (DPWH)
View all 467 projects →

4. Implementation

Contract Amount

₱9,434,776.41

Progress

Reported complete (DPWH)

Start Date

January 20, 2020

Target End

April 18, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.