Bridges15CN0132

REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGES, MIJARES BRIDGE (B03017LZ) ALONG BALER-CASIGURAN RD. (BALER-DINADIAWAN)

REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGES, MIJARES BRIDGE (B03017LZ) ALONG BALER-CASIGURAN RD. (BALER-DINADIAWAN) is a DPWH-tracked public work in Aurora DEO, Region III. Reported contract value: ₱1,675,556.43. Status: Reported complete (DPWH). Contractor on record: ZF CONST. Figures trace to dpwh.

Aurora DEO, Region III
Region: Region III

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Flood Control Project (Riprap Revetment), Brgy. Pingit, Baler, Aurora Lone District
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROV-16-0026246

₱890,370.00 · FY2016

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱1,675,556.43

Progress

Reported complete (DPWH)

Start Date

February 16, 2016

Target End

April 6, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.