Flood Control and Drainage17PL0019

REHABILITATION OF TAGA BRIDGE FLOOD CONTROL ALONG SALTAN RIVER

REHABILITATION OF TAGA BRIDGE FLOOD CONTROL ALONG SALTAN RIVER is a DPWH-tracked public work in Lower Kalinga DEO, Cordillera Administrative Region. Reported contract value: ₱4,664,980.51. Status: Reported complete (DPWH). Contractor on record: CASIGAYAN CONST. Figures trace to dpwh.

Lower Kalinga DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Bonog Bridge Flood Control along Chico River, Kalinga
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-17-0008275

₱255,507.00 · FY2017

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱4,664,980.51

Progress

Reported complete (DPWH)

Start Date

April 19, 2017

Target End

August 16, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.