Flood Control and Drainage21KK0107

CONSTRUCTION OF FLOOD CONTROL (UPSTREAM), STA. INES BRIDGE 2, TALISAYAN, MISAMIS ORIENTAL

CONSTRUCTION OF FLOOD CONTROL (UPSTREAM), STA. INES BRIDGE 2, TALISAYAN, MISAMIS ORIENTAL is a DPWH-tracked public work in Misamis Oriental 1st DEO, Region X. Reported contract value: ₱97,989,043.64. Status: Reported complete (DPWH). Contractor on record: JEJOR'S CONST CORP. Figures trace to dpwh.

Misamis Oriental 1st DEO, Region X
Region: Region X

Money Trail

1. Appropriation

Probable match · score 97%

UACS
18001
Amount
₱100,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control (Upstream), Sta. Ines Bridge 2, Talisayan, Misamis Oriental
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Misamis Oriental 1st DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱97,989,043.64

Progress

Reported complete (DPWH)

Start Date

March 25, 2021

Target End

March 7, 2022

5. Audit