Roads22OH0022

ORGANIZATIONAL OUTCOME 1:ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE-SECONDARY ROADS-P. BURGOS ST. K0001+(-192)-K0001+(-25),K0001+(-460)-K0001+(-192)

ORGANIZATIONAL OUTCOME 1:ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE-SECONDARY ROADS-P. BURGOS ST. K0001+(-192)-K0001+(-25),K0001+(-460)-K0001+(-192) is a DPWH-tracked public work in South Manila DEO, National Capital Region. Reported contract value: ₱13,630,024.95. Status: Reported complete (DPWH). Contractor on record: AARCON BUILDERS 28336. Figures trace to dpwh.

South Manila DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Possible match · score 76%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Flood Control Structures and Facilities along Earnshaw St., (Estero de San Miguel to A.H. Lacson Ave.) and Antipolo St., (G. Tuazon to Espana Blvd.), Manila City
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

South Manila DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

Not graded

DPWH ID 28336

361 projects · ₱9.9B total · 0 flags

Other projects by this contractor

DREDGING OF GUAGUA-PASAC RIVER, SASMUAN, PAMPANGA

Flood Control Management Cluster, Central Office

2018₱187.5M
Reported complete (DPWH)
No sat.

ASSET PRESERVATION - PREVENTIVE MAINTENANCE - PRIMARY ROADS - EPIFANIO DELOS SANTOS AVE (EDSA) - K0021 + (-158) - K0021 + 000, K0021 + (-229) - K0021 + (-158), K0021 + 000 - K0025 + 163

National Capital Region, National Capital Region

2024₱160.5M
Reported complete (DPWH)
No sat.

PREVENTIVE MAINTENANCE - PRIMARY ROADS - MANILA-CAVITE (NCR BDRY-JCT CAVITE CITY SECT) - K0015 + 985 - K0016 + 087, K0016 + 303 - K0016 + 651; MC DONALD JCT-AGUINALDO H-WAY - K0015 + 274 - K0015 + 690 AND MANILA-CAVITE (NCR BDRY-JCT CAVITE CITY SECT) - K

Cavite 3rd DEO, Region IV-A

2025₱140.9M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEMASSET PRESERVATION PROGRAMREHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADSKAWIT-NOVELETA DIV RD. - K0024 + 495 - K0025 + 438

Cavite 1st DEO, Region IV-A

2025₱103.9M
Reported complete (100% progress, DPWH status On-Going)

PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS CONSTRUCTION OF BACOOR FLOOD CONTROL PROJECT INCL. A PUMPING STATION, (PACKAGE A), BACOOR CITY, CAVITE

Region IV-A, Region IV-A

2019₱103.0M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - TERTIARY ROADS - ASPHALT OVERLAY OF TANAY-SAMPALOC RD - K0066+100 - K0068+000, K0069+000 - K0070+443, TANAY, RIZAL

Rizal 2nd DEO, Region IV-A

2024₱98.0M
Reported complete (DPWH)
View all 361 projects →

4. Implementation

Contract Amount

₱13,630,024.95

Progress

Reported complete (DPWH)

Start Date

February 28, 2022

Target End

March 29, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.