Roads22DF0013

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM, CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO SEAPORTS (KALSADA TUNGO SA PALIPARAN, RILES, AT DAUNGAN PROGRAM - KATUPARAN),CALIBUYO ROAD LEADING TO CAVITE GATEWAY TERMINAL, TAN

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM, CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO SEAPORTS (KALSADA TUNGO SA PALIPARAN, RILES, AT DAUNGAN PROGRAM - KATUPARAN),CALIBUYO ROAD LEADING TO CAVITE GATEWAY TERMINAL, TAN is a DPWH-tracked public work in Cavite 1st DEO, Region IV-A. Reported contract value: ₱46,202,100.00. Status: Reported complete (DPWH). Contractor on record: J M MALIGAYA CONST CORP FORMERLY: J M MALIGAYA CONST. Figures trace to dpwh.

Cavite 1st DEO, Region IV-A
Region: Region IV-A

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 79%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure (Riprap), Barangay 9 Road, Amadeo, Cavite
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Cavite 1st DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

54 projects · ₱2.0B total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM,NETWORK DEVELOPMENT, CONSTRUCTION OF MISSING LINKS/NEW ROADS-GENERALAGUINALDO-MAGALLANES-NASUGBU ROAD (EAST-WEST ROAD), AMADEO SECTION,CAVITE

Cavite 1st DEO, Region IV-A

2019₱96.5M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF MISSING LINKS / NEW ROADSGENERAL AGUINALDO - MAGALLANES - NASUGBU ROAD(EAST - WEST ROAD), INDANG - WEST SECTION, CAVITE

Region IV-A, Region IV-A

2023₱96.5M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF MISSING LINKS/ NEW ROADS GENERAL AGUINALDO - MAGALLANES - NASUGBU ROAD (EAST-WEST ROAD), INDANG-WEST SECTION, CAVITE

Region IV-A, Region IV-A

2022₱95.4M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEMNETWORK DEVELOPMENTCONSTRUCTION OF BY-PASS AND DIVERSION ROADSDASMARINAS - GENERAL TRIAS - TANZA (PUNTA - BAGTAS SECTION), TANZA, CAVITE

Cavite 1st DEO, Region IV-A

2025₱95.0M
Past target date (DPWH On-Going)
No sat.

LOCAL PROGRAM - LOCAL INFRASTRUCTURE PROGRAM, LOCAL ROADS AND BRIDGES, LOCAL ROADS CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS, CONSTRUCTION OF INDANG-CABUCO-NAIC DIVERSION ROAD, TRECE MARTIRES CITY

Cavite 1st DEO, Region IV-A

2020₱94.6M
Reported complete (DPWH)
No sat.

LOCAL PROGRAMCONST. / REPAIR / REHAB. / IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTSLOCAL ROADS AND BRIDGESLOCAL BRIDGECONSTRUCTION OF SAHUD ULAN BRIDGE ALONG SAHUD ULAN-TRES CRUSES-TMC ROAD, BARANGAY TRES CRUSES SECTION, TANZA,

Cavite 1st DEO, Region IV-A

2021₱93.6M
Reported complete (DPWH)
View all 54 projects →

4. Implementation

Contract Amount

₱46,202,100.00

Progress

Reported complete (DPWH)

Start Date

February 24, 2022

Target End

January 7, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.