Roads24FG0002

PREVENTIVE MAINTENANCE (ASPHALT OVERLAY) ALONG LAGONOY-PRESENTACION ROAD, SECTION 1: K0499+077.00 - K0499+540.00; SECTION 2: K0499+700.00 - K0500+400.00, LAGONOY, CAMARINES SUR

PREVENTIVE MAINTENANCE (ASPHALT OVERLAY) ALONG LAGONOY-PRESENTACION ROAD, SECTION 1: K0499+077.00 - K0499+540.00; SECTION 2: K0499+700.00 - K0500+400.00, LAGONOY, CAMARINES SUR is a DPWH-tracked public work in Camarines Sur 4th DEO, Region V. Reported contract value: ₱19,985,089.20. Status: Reported complete (DPWH). Contractor on record: NFH CONST. Figures trace to dpwh.

Camarines Sur 4th DEO, Region V
Region: Region V

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱53,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure ( Rangas River ) along Jct. Nato - Sabang Coastal Road, Barangay Telegrafo, San Jose, Camarines Sur
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Camarines Sur 4th DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

123 projects · ₱5.3B total · 0 flags

Other projects by this contractor

No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BYPASS AND DIVERSION ROADS-MABOLO-ALMEDA BYPASS ROAD, NAGA CITY, CAMARINES SUR 3RD LEGISLATIVE DISTRICT

Region V, Region V

2021₱226.8M
Reported complete (DPWH)
No sat.

CONST./IMPV'T. OF ACCESS ROADS LEADING TO AIRPORTS, SEAPORTS AND DECLARED TOURISM DESTINATIONS - JCT. MORNING, CATAINGAN-ESPERANZA PORT ROAD, PIO V. CORPUZ AND ESPERANZA, MASBATE 3RD LD

Region V, Region V

2016₱202.4M
Reported complete (DPWH)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS-CAMARINES SUR EXPRESSWAY PACKAGE 7, CAMARINES SUR, PILI, CAMARINES SUR (3RD LEGISLATIVE DISTRICT)

Region V, Region V

2023₱193.0M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE-SECONDARY ROADS -NASUGBU-LIAN-CALATAGAN RD (S05012LZ) - K0113 + 600 - K0114 + 000, K0115 + 000 - K0116 + 400

Batangas 1st DEO, Region IV-A

2024₱144.8M
Reported complete (DPWH)
No sat.

CONST./IMPV'T. OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS, ROAD UPGRADING (GRAVEL TO CONCRETE) OF SAN JUAN-ALAS-TAGPU-DAYAO ROAD LEADING TO MANDAON ECOTOURISM SITES, MANDAON, MASBATE PROVINCE

Region V, Region V

2016₱144.7M
Reported complete (DPWH)
No sat.

ROAD UPGRADING (UNPAVED TO PAVED) BASED ON GRAVEL ROAD STRATEGIES, TRAFFIC BENCHMARK FOR UPGRADING TO PAVED ROAD STANDARDS (HDM-4 PROJECT ANALYSIS) STA. ELENA - CAPALONGA BY PASS COASTAL ROAD, KO283+040 - KO292+200 WITH EXCEPTIONS, CAMARINES NORTE

Region V, Region V

2016₱142.9M
Reported complete (DPWH)
View all 123 projects →

4. Implementation

Contract Amount

₱19,985,089.20

Progress

Reported complete (DPWH)

Start Date

March 14, 2024

Target End

May 9, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

PREVENTIVE MAINTENANCE (ASPHALT OVERLAY) ALONG LAGONOY-PRESENTACION ROAD, SECTION 1: K0499+077.00 - K0499+540.00; SECTION 2: K0499+700.00 - K0500+400.00, LAGONOY, CAMARINES SUR | ❤️ THE 🇵🇭