Buildings and Facilities17EH0092

CONSTRUCTION OF ELEMENTARY AND SECONDARY CLASSROOMS, 1STY2CL SAN JOSE ES, ROMBLON, ROMBLON

CONSTRUCTION OF ELEMENTARY AND SECONDARY CLASSROOMS, 1STY2CL SAN JOSE ES, ROMBLON, ROMBLON is a DPWH-tracked public work in Romblon DEO, Region IV-B. Reported contract value: ₱2,520,716.89. Status: Reported complete (DPWH). Contractor on record: ST PIUS CONST AND SUPPLY. Figures trace to dpwh.

Romblon DEO, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2017 GAA. DBM GAA FY2017

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-17-0001876

₱7,524.00 · FY2017

Released to University of Eastern Philippines (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

31 projects · ₱1.3B total · 0 flags

Other projects by this contractor

SUSTAINABLE INFRASTUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF CAUSEWAY FOR TOURISM ALONG AMBULONG PORT, MAGDIWANG, SIBUYAN ISLAND, ROMBLON

Region IV-B, Region IV-B

2023₱289.5M
Reported complete (DPWH)

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF COASTAL ROAD/BOULEVARD & CAUSEWAY FOR TOURISM ALONG SABLAYAN PORT, ROMBLON, ROMBLON

Region IV-B, Region IV-B

2023₱289.5M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS TO AUGMENT RESILIENCY OF COASTAL COMMUNITIES- CONST. OF COASTAL ROAD/SHORE PROTECTION ALONG BRGY. CAMBIJANG-BRGY. POBLACION, STA. 000+748.60-STA. 001+020, CAJIDIOCAMN, ROMBLON

Region IV-B, Region IV-B

2025₱230.9M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE ALLEVIATING GAPS (SIPAG)- COASTAL ROADS TO AUGMENT RESILIENCY OF COASTAL COMMUNITIES- CONST. OF COASTAL ROAD/SHORE PROTECTION ALONG BRGY. CAMBIJANG, STA. 000+398.65-STA. 000+440; STA. 000+520-STA. 000+740, CAJIDIOCAN, SIBUYAN IS

Region IV-B, Region IV-B

2025₱230.9M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF SAWANG FLOOD CONTROL STRUCTURE, ROMBLON, ROMBLON

Romblon DEO, Region IV-B

2025₱54.2M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONSTRUCTION OF AGNIPA GRAND STAND IN AGNIPA ELEMENTARY SCHOOL GROUND, BARANGAY AGNIPA, ROMBLON, ROMBLON

Romblon DEO, Region IV-B

2025₱29.3M
Past target date (DPWH On-Going)
View all 31 projects →

4. Implementation

Contract Amount

₱2,520,716.89

Progress

Reported complete (DPWH)

Start Date

January 23, 2018

Target End

April 17, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.