Roads22IC0082

CONCRETING OF BRGY. MALAGUINABOT TO BRGY. CAPILIHAN FMR PHASE II, BRGY. MALAGUINABOT AND BRGY. CAPILIHAN, SAN MIGUEL, LEYTE

CONCRETING OF BRGY. MALAGUINABOT TO BRGY. CAPILIHAN FMR PHASE II, BRGY. MALAGUINABOT AND BRGY. CAPILIHAN, SAN MIGUEL, LEYTE is a DPWH-tracked public work in Leyte 1st DEO, Region VIII. Reported contract value: ₱12,427,500.00. Status: Reported complete (DPWH). Contractor on record: CORILLO BUILDERS AND SUPPLY. Figures trace to dpwh.

Leyte 1st DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control along Mainit River, Brgy. Capilihan, San Miguel, Leyte
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Leyte 1st DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

4. Implementation

Contract Amount

₱12,427,500.00

Progress

Reported complete (DPWH)

Start Date

June 28, 2022

Target End

October 20, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.