Buildings and Facilities23DD0115

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING AT INOSLUBAN-MARAWOY INTEGRATED HIGH SCHOOL, BARA

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING AT INOSLUBAN-MARAWOY INTEGRATED HIGH SCHOOL, BARA is a DPWH-tracked public work in Batangas 4th DEO, Region IV-A. Reported contract value: ₱9,501,230.00. Status: Reported complete (DPWH). Contractor on record: TERAVERA CORP. Figures trace to dpwh.

Batangas 4th DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Pinagsibaan Bridge 2, Rosario, Batangas
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Batangas 4th DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

211 projects · ₱2.4B total · 0 flags

4. Implementation

Contract Amount

₱9,501,230.00

Progress

Reported complete (DPWH)

Start Date

April 2, 2023

Target End

June 30, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.