Flood Control and Drainage19DI0044

CONSTRUCTION OF RIVER CONTROL ALONG CABUYAO RIVER, BRGY. BIGAA, CABUYAO CITY, LAGUNA

CONSTRUCTION OF RIVER CONTROL ALONG CABUYAO RIVER, BRGY. BIGAA, CABUYAO CITY, LAGUNA is a DPWH-tracked public work in Laguna 2nd DEO, Region IV-A. Reported contract value: ₱48,991,503.80. Status: Reported complete (DPWH). Contractor on record: HARVEE ENT 33927. Figures trace to dpwh.

Laguna 2nd DEO, Region IV-A
Region: Region IV-A

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2019 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱48,991,503.80

Progress

Reported complete (DPWH)

Start Date

July 3, 2019

Target End

February 18, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.